The refurb works are going fantastically - a week ahead of schedule! All the room partitions are up, the toilets are no longer a big horrible area (now a big partitioned area with no actual toilets in them yet), the ducting for the dental chairs in place, and we're giving the cross-infection control room a lot of thought.
The builders, electricians, painters, plasterers are all great. They work like demons and are unfailingly courteous and helpful, even when I'm on site looking bemused and generally getting in the way.
This shows the partition in place for one of the two surgeries that we're having. The area by the window is going to be the main entrance and disabled access from the car-park.
Here's the main-door-to-be again on the left. The rest of the area will be reception (desk near the door). The door on the right of the scaffolding tower is to the toilets. All the wires in the ceiling will be covered by a new suspended ceiling once the ducting for the air-con system is in place.
And the toilets! Perhaps enough said. The